Most jack-ups aren't built to cross oceans under their own power. When one has to change regions, the choice is usually between towing it (a wet tow) or carrying it on the deck of a semi-submersible heavy-transport vessel (a dry tow, or dry transport). Several recent moves show both options in action.

Four recent moves

How a float-on works

A semi-submersible heavy-transport vessel can ballast down until its cargo deck is under water. The floating cargo is then manoeuvred into position over the deck, usually with tugs and winches. Once it's lined up over the cribbing, the vessel pumps out ballast and rises, lifting the cargo clear of the water. Float-off is the same in reverse.

It sounds simple. In practice, it's a planned marine operation with very little margin for error.

Ballast and weather windows

Cribbing and seafastening

Surveyor and MWS sign-off

A marine warranty surveyor (MWS) is usually appointed on behalf of the insurers. They review the engineering (stability, ballast plan, cribbing and seafastening design, weather limits) before the job and attend the operation. The vessel shouldn't sail until the MWS issues a certificate of approval.

The Ralph Coffman post is a reminder that a float-on also needs an agent, customs formalities and port coordination on the ground, not just engineering.

Wet tow or dry transport?

There's no single right answer. The Valaris 104 move used both. Points that usually decide it:

A quick checklist for a dry transport

  1. Cargo data: weight, centre of gravity, dimensions, leg positions and strong points.
  2. Vessel suitability: deck size, submersion depth and stability with the cargo.
  3. Load-out site: depth, shelter, permits and agency.
  4. Engineering: ballast plan, cribbing layout, seafastening design and motion criteria.
  5. MWS appointed early, with the engineering submitted for review.
  6. Weather criteria and forecast service agreed.
  7. Customs, port and agency formalities at both ends.
  8. Float-off plan at the destination.

Sources

  • HMT News, BOKA Vanguard transports VALARIS 106 to Indonesia, Sept 2026. Read the source
  • Offshore Magazine, Rig roundup: Noble, Borr and Transocean win drilling contracts while Valaris assists in Mako project, 17 Sep 2026. Read the source
  • Inchcape Shipping Services (Mexico), LinkedIn post, ISS Mexico supports transport of VALARIS jack-up Ralph Coffman aboard Blue Marlin, 16 Jul 2026. Read the source
  • HMT News, Boskalis Forte completes Starship transport, 9 Oct 2026. Read the source

HMT News says its articles are AI-assisted and edited, so we attribute its facts as "reported by" and you should check them before relying on them. The Inchcape item is a company LinkedIn post, not independent news.

The "how it works" sections describe general industry practice. They're not a method statement. Every float-on is engineered for its own cargo, vessel and site.