Lashed & Secured editorial team · October 2026 · 6 min read

A large offshore construction vessel alongside, with its accommodation block and a red crane
Photo: Julia Taubitz / Unsplash

A run of orders over the last few months points to a lot of new heavy-lift and heavy-transport tonnage arriving between 2028 and 2031. Here's what's been announced, and the questions it raises for anyone moving breakbulk, out-of-gauge or project cargo. This is analysis, not a forecast. Nobody knows yet what rates will do.

What's been ordered

OwnerWhatKey specsDeliverySource
COSCO Shipping Specialized Carriers8 multi-purpose heavy-lift vessels60,000 dwt each. About US$392m in total, roughly US$49m a ship. Built in China.2029–30World Ports Organization, 29 Sep 2026
SAL Heavy LiftMoU for 5 more Orca-class ships14,600 dwt, 2 × 800 t cranes (1,600 t in tandem), built at Wuhu. A non-binding MoU signed at SMM Hamburg on 3 Sep. It would take the series to 10.Not stated in our sourceAs reported by HMT News, 7 Sep 2026 (also covered by Seatrade Maritime and PortNews)
Jumbo2 L-class heavy-lift ships25,000 dwt, 2 × 1,200 t Huisman cranes, built at Dajin2028–29Jumbo Maritime, 26 May 2026
AllseasGrand Tour heavy-transport vessel60,000 t capacity, 230 × 57 m, built at GSI, China. Sized to slot into Pioneering Spirit's bow for 2 GW converter topsides.Q1 2028Offshore Magazine, 5 Oct 2026
Cadeler2 T-class wind installation vesselsAbout €805m for the pair. Built in China.2030 and 2031Cadeler, 10 Aug 2026

Reports differ on which yard is building the COSCO ships, so we haven't named it.

Not all of this is "space" for your cargo

It helps to split the list in two.

What it could mean for space and rates

More capable ships usually mean more options. Whether that turns into easier space or lower rates depends on things these announcements don't tell us:

Questions worth asking now

  1. For projects shipping in 2028–31, which carriers will have ships with the lift capacity and deck space you need?
  2. Is your heaviest piece in a crane band where new capacity is coming, or one where it's still tight?
  3. Will your cargo be competing for the same ships as offshore wind campaigns in those years?
  4. Are long-term contract offers based on today's market or on the new ships coming?

Sources

  • World Ports Organization, Order for eight 60,000 dwt multi-purpose heavy-lift vessels, 29 Sep 2026. Read the source
  • HMT News, SAL Heavy Lift signs MOU for five more Orca Class vessels, 7 Sep 2026. Read the source
  • Jumbo Maritime, Jumbo orders a new class of versatile heavy lift vessels, 26 May 2026. Read the source
  • Offshore Magazine, Allseas begins construction of heavy-transport vessel for offshore megaprojects, 5 Oct 2026. Read the source
  • Cadeler press release (Business Wire), Cadeler strengthens future installation capacity with firm orders for two new T-class vessels, 10 Aug 2026. Read the source

HMT News says its articles are AI-assisted and edited, so we attribute its facts as "reported by" and you should check them before relying on them. The Jumbo and Cadeler items are company announcements, not independent news.