Out-of-gauge cargo

PHPD Per hatch per day

Chartering

A laytime rate set per hatch per day. Laytime is the cargo quantity divided by the daily rate times the number of hatches.

Example

30,000 t at 1,000 t PHPD with 5 hatches gives 6 days' laytime.