Laycan vs laytime When the ship must arrive, and how long cargo work may take

Mix-ups

Laycan is a window of dates: the ship must be ready to load inside it, or the charterer may cancel. Laytime is an allowance of time: how long the charterer has to load or discharge before demurrage starts. A ship can arrive well inside the laycan and still run over its laytime.

Worked example

Laycan 10–15 Nov, laytime 48 hours SHINC. The ship is ready on 12 Nov, so there is no right to cancel. Laytime starts 12 Nov 14:00 and runs out 14 Nov 14:00.

  1. Laycan 10–15 Nov: ship ready 12 Nov, inside the window
  2. Laytime 48 hours SHINC, from 12 Nov 14:00
  3. Laytime ends 14 Nov 14:00
  4. Discharge ends 15 Nov 02:00: 12 hours on demurrage

The terms

Sources

Checked 27 Oct 2026 · next check January 2027. Meanings can differ by trade and contract: check your own documents.